Designated Area of Responsibility
"Jeddah Clearance" (OEJN_DEL) will be responsible of issuing IFR clearances for all departure traffic from Jeddah and the transfer of traffic requesting push to the correct ground controller.
Notes
Departure
- IFR clearances in Jeddah include the departure runway, the SID, the initial climb, and the squawk using the prescribed phraseology in the SOP.
- The initial climb for all SIDs is 6000ft.
- Departure traffic shall only be cleared on RWY 34C/16C regardless of their stand or requests as SDRO will be in use during the whole event to increase the arrival runway capacity.
- Departure traffic shall be handed off to "Jeddah Apron" (OEJN_E_RMP) if at Apron 7, 6, A, B, C or to the respective "Jeddah Ground" controller if at Apron 1, 2, 3, 4, 5.